CELLARHEAD BESS · 33 kV DUCTING

As-built quantities & weekly progress

Open this scope in 3D

Provisional survey-based QS report. Dates come from survey layers, not installation sign-off. Straight, bent and curved sections are measured along the original 3D linework. Polyline bends are identified by plan deflections of at least 10°; both incident edges enter the bend section. Review section limits before valuation. A section is not a manufactured bend fitting.

Location & comparison basis

Automatic target: BESS 33KV DUCTING OFFICIAL SO.dxf, the lower and upper duct layers in the existing model. Each individual duct contributes its length; this is not trench-centreline length or a count of installed cables. Excavation and concrete lines have separate quantities and do not enter the duct completion percentage.

As-built over design

North up · blue = official design, target only · other colours = dated as-built. Grey = unassigned survey date when included. No survey point symbols. Actual 3D levels and line lengths are available by selecting an element in the viewer.

Weekly QS quantities · as-built only

Calendar weeks, Monday–Sunday. Counts refer to contiguous source sections split at survey dates and the straight/bend rule; location boundaries may split them further. Metres follow 3D geometry, including its bends. Curved polylines retain measured chords; splines are sampled using a 1 mm flattening setting. Section counts and metres are not payable fitting quantities.

Week startingFeatureStraight sectionsStraight mBend sectionsBend mSpline sectionsSpline mTotal 3D mInferred date sections

Weekly comparison against design

New weekly coverage = union of matched design intervals to week end minus the union before that week. Repeated survey coverage is therefore counted once. Dated observations only; unresolved or ambiguous matches cannot establish completion. The remaining figure means design length without dated, unambiguous survey coverage.

Week startingDesign target mNew coverage mNew % of targetCovered to date mCovered %Remaining mRemaining %

Daily measured quantities

Survey dayFeatureStraight mBend mSpline mTotal 3D mSectionsInferred date sections

Review & exclusions

Line schedule · selected scope

Only dated sections in the chosen period, plus unassigned sections when requested. Full E/N/Z end coordinates, supporting point IDs, point layers, association residuals and date rules are in the CSV. An inferred-section count flags provenance, not a date-layer conflict.

Source / edgesDateFeatureClass3D mPlan mZ min mZ max mDate evidence